Another Pipeline Blocked for Failure to Consider Climate Emissions
View
Date:2025-04-26 09:34:55
[UPDATE: On Sept. 15, FERC overrode New York’s decision on the Valley Lateral Project, stating that New York officials had missed a deadline to act. Bloomberg BNA discusses that move and the likelihood that the state will appeal, here.]
It might be getting harder to win approval for new fossil fuel projects without first examining their impacts on climate change. Last week, regulators in New York rejected key permits for a natural gas pipeline, saying a previous federal approval had failed to consider the resulting greenhouse gas emissions.
The pipeline in question, the 7.8 mile-long Valley Lateral Project, would supply a 680 megawatt power plant that’s currently under construction. The pipeline had already received approval from the Federal Energy Regulatory Commission (FERC), but because it crosses several streams and wetlands, it needed state regulators to sign off, too.
In a letter to FERC on Aug. 30, Thomas Berkman, deputy commissioner and general counsel at the New York Department of Environmental Conservation, wrote that federal regulators had “failed to consider or quantify the indirect effects” of the emissions produced when the fuel shipped through the pipeline is eventually burned.
The state cited a federal court ruling issued just one week earlier as its justification for denying the permits. In that case, a federal circuit court in Washington, D.C., rejected an approval by FERC of a separate pipeline in the Southeast, saying “FERC must either quantify and consider the project’s downstream carbon emissions or explain in more detail why it cannot do so.”
Berkman wrote that that court decision constitutes “a material change in applicable law” and that the commission should therefore reexamine the Valley Lateral application.
Other Fossil Fuel Projects Blocked
Courts or regulators have blocked fossil fuel projects several times in the past month, at least in part because federal agencies failed to account for downstream climate emissions. On Aug. 14, a federal district judge in Montana rejected a proposed expansion of a coal mine in that state, saying the U.S. Department of Interior hadn’t adequately considered climate and other impacts.
New York’s denial of the permit is the latest in a series of decisions by Gov. Andrew Cuomo’s administration to block natural gas projects since he banned hydraulic fracturing in the state in 2014. In April, the state denied permits for a proposed pipeline from Pennsylvania’s gas fields. A year earlier, it blocked another interstate pipeline. In both cases, the projects had received federal approval but required the same type of permits from the state under the Clean Water Act.
In this case, however, the state did not actually rule on the water permits themselves, but instead sent the case back to FERC to review the climate impacts.
Challenging the Pipeline Boom
“I don’t know why the DEC chose this procedural argument,” said Pramilla Malick, of the local advocacy group Protect Orange County. “Ultimately, the DEC has a legal and moral authority to protect water quality” and deny the permits outright, she said. “They have basically kicked it to FERC.”
Malick’s group has been fighting a buildout of natural gas infrastructure in New York’s Orange County since 2011, and she said the state’s previous approvals of the CPV Valley Energy Center, the power plant that would be supplied by the Valley Lateral pipeline, were contrary to Cuomo’s climate policies and his rejection of fracking.
The plant is also at the center of corruption charges that were brought by federal prosecutors last year against two Cuomo aides. One of the aides, Joseph Percoco, is charged with taking bribes from Competitive Power Ventures, the company behind the plant, while a former company official is also named as a defendant. The case has yet to go to trial.
The opposition to the pipeline and the power plant has drawn support from national environmental groups and advocates, including Bill McKibben, who attended a rally in August. They’ve argued that the power plant would substantially increase the state’s greenhouse gas emissions, and they called on the state to reject the pipeline as a way to stop the plant.
Michelle Hook, a spokeswoman for Millennium Pipeline Company, which proposed the Valley Lateral Project, said in a statement that the state’s ruling “does not appear to be a clear-cut decision and our lawyers are reviewing it to determine how to proceed,” adding “the agency’s issue is with the power plant’s greenhouse gas emissions and not any direct environmental impact of our pipeline.”
Competitive Power Ventures, the company building the power plant that was to burn the gas shipped through the Valley Lateral line, told the Times Herald-Record last week that the company would proceed with its plans to finish the plant and called the state’s decision “without merit.”
Wider Implications?
It’s unclear whether the latest developments will affect another project—a proposed expansion of a gas storage facility in New York’s Finger Lakes region—that’s awaiting state approval and has also prompted a vibrant grassroots opposition.
The original proposal would have increased capacity at an existing natural gas storage facility and added storage of liquefied petroleum gas. While the natural gas piece of the project received federal approval in 2014, it spurred a years-long civil disobedience campaign and construction never began.
In May, the company behind the project announced it was abandoning the natural gas portion because it couldn’t secure enough contracts from customers. The liquefied gas piece, however, is overseen by the state, which has not yet issued a ruling. In lobbying against the project, opponents have cited its impacts on water and climate change.
veryGood! (51)
Related
- South Korea's acting president moves to reassure allies, calm markets after Yoon impeachment
- Julie Chrisley's Heartbreaking Prison Letters Detail Pain Amid Distance From Todd
- A pregnant Amish woman is killed in her rural Pennsylvania home, and police have no suspects
- Taylor Swift's father allegedly punched photographer in face after Australian leg of her Eras Tour ended
- San Francisco names street for Associated Press photographer who captured the iconic Iwo Jima photo
- 'Sopranos' star Drea de Matteo says OnlyFans 'saved' her after vaccine stance lost her roles
- TikTokers are using blue light to cure acne. Dermatologists say it's actually a good idea.
- FBI, state investigators seek tips about explosive left outside Alabama attorney general’s office
- North Carolina trustees approve Bill Belichick’s deal ahead of introductory news conference
- Toronto Blue Jays reliever Erik Swanson away from team after 4-year-old son gets hit by car
Ranking
- Newly elected West Virginia lawmaker arrested and accused of making terroristic threats
- Essential winter tips on how to drive in the snow from Bridgestone's winter driving school
- Florida Senate unanimously passes bill to define antisemitism
- FBI offers $15,000 reward in case of missing Wisconsin boy
- Juan Soto praise of Mets' future a tough sight for Yankees, but World Series goal remains
- Louisiana moves closer to final passage of tough-on-crime bills that could overhaul justice system
- Horoscopes Today, February 27, 2024
- Actor Buddy Duress Dead at 38
Recommendation
Israel lets Palestinians go back to northern Gaza for first time in over a year as cease
TIMED spacecraft and Russian satellite avoid collision early Wednesday, NASA confirms
Schumer describes intense White House meeting with Johnson under pressure over Ukraine aid
American women's cycling team suspended after dressing mechanic as a rider to avoid race disqualification
Could your smelly farts help science?
Messi, Argentina plan four friendlies in the US this year. Here's where you can see him
'The Voice': Watch the clash of country coaches Reba and Dan + Shay emerge as they bust out blocks
Boeing given 90 days by FAA to come up with a plan to improve safety and quality of manufacturing